
The
Seikan Tunnel
is a 53.85 km (33.46 mi) railway tunnel in Japan, with a 23.3-kilometre
(14.5 mi) long portion under the seabed. Track level is about 140-metre
(460 ft) below seabed and 240-metre (790 ft) below sea level. It is the
longest undersea tunnel in the world, although the
Channel Tunnel
between the United Kingdom and France has a longer under-sea portion.
It travels beneath the Tsugaru Strait—connecting Aomori Prefecture on
the Japanese island of Honshū and the island of Hokkaidō—as part of the
Kaikyo Line of Hokkaido Railway Company. Although it is the longest
traffic (railway or road) tunnel in the world, faster and cheaper air
travel has left the Seikan Tunnel comparatively underused. Its claim to
the record for the longest tunnel will be taken when the Gotthard Base
Tunnel, a European railway tunnel, is completed in around 2018. It is
also the deepest rail tunnel in the world.

Surveying, construction and geology
Surveying
started in 1946 and in 1971, twenty-five years later, construction
began. By August 1982, less than 700 metres of the tunnel remained to be
excavated. First contact between the two sides was in 1983.
The
Tsugaru Strait has eastern and western necks, both approximately 20
kilometres across. Initial surveys undertaken in 1946 indicated that the
eastern neck was up to 200 metres deep with volcanic geology. The
western neck had a maximum depth of 140 metres and geology consisting
mostly of sedimentary rocks of the Neogene period. The western neck was
selected, with its conditions considered favourable for tunnelling.
Geology of the undersea portion of the tunnel consists of volcanic
rock, pyroclastic rock, and sedimentary rock of the late Tertiary era.
The area is folded into a nearly vertical anticline, which means that
the youngest rock is in the centre of the Strait, and encountered last.
Divided roughly into thirds, the Honshū side consists of volcanic rocks
(andesite, basalt etc); the Hokkaidō side consists of sedimentary rocks
(Tertiary period tuff, mudstone, etc); and the centre portion consists
of Kuromatsunai strata (Tertiary period sand-like mudstone). Igneous
intrusions and faults caused crushing of the rock and complicated the
tunnelling procedures.
Initial geological investigation occurred
from 1946–1963 which involved drilling the sea-bed, sonic surveys,
submarine boring, observations using a mini-submarine, and seismic and
magnetic surveys. To establish a greater understanding, a horizontal
pilot boring was undertaken along the line of both the service and pilot
tunnels.
Tunnelling occurred simultaneously from both the northern and southern
ends. The dry land portions were tackled with traditional mountain
tunnelling techniques, with a single main tunnel. However, for the
23.3-kilometre undersea portion, three bores were excavated with
increasing diameters respectively: an initial pilot tunnel, a service
tunnel, and finally the main tunnel. The service tunnel was periodically
connected to the main tunnel with a series of connecting shafts, at
600- to 1,000-metre intervals. The pilot tunnel serves as the service
tunnel for the central five-kilometre portion.
Beneath the
Tsugaru Strait, the use of a tunnel boring machine (TBM) was abandoned
after less than two kilometres owing to the variable nature of the rock
and difficulty in accessing the face for advanced grouting. Blasting
with dynamite and mechanical picking were then used to excavate.
Structure
Originally only narrow gauge track was laid through the tunnel, but in
2005 the Hokkaidō Shinkansen project started construction has included
laying dual-gauge track and linking the tunnel into the Shinkansen
network. Shinkansen trains will be able to traverse the tunnel to
Hakodate from 2015 and eventually Sapporo. The tunnel has 52 kilometres
of continuous welded rail. Two stations are located within the tunnel
itself: Tappi-Kaitei Station and Yoshioka-Kaitei Station. The stations
serve as emergency escape points. In the event of a fire or other
disaster, both stations provide the equivalent safety of a much shorter
tunnel. The effectiveness of the escape shafts located at the emergency
stations is enhanced by having exhaust fans to extract smoke, television
cameras to help route passengers to safety, thermal (infrared) fire
alarm systems, and water spray nozzles.
Previously, both the
stations contained museums detailing the history and function of the
tunnel and which could be visited on special sightseeing tours. Only
Tappi-Kaitei remains as a museum, the museum function at Yoshioka-Kaitei
was closed on 16 March 2006 to provide a storage room for work on the
upgrades related to the Hokkaidō Shinkansen service.
The two stations were the first railway stations in the world built under the sea.
Source
source
0 comments:
Post a Comment